Page 2 - Hunstanton Town & Around - January 2015
P. 2

2 Hunstanton Town & Around January 2015                                   Tel: 01485 533422 email: editor@townandaround.net
       A149 ROAD WORKS AND CLOSURES                        traffic to pass through the works.
                                                            In regards to the diversion routes Diversion Route 1 will be used
       Norfolk County Council will commence road works in Hunstanton  between 16 March – 27 March 2015 and Diversion Route 2 will be
       on Monday 16 February for a duration of 6 weeks (not including  in place from 16 February – 13 March 2015.  The reason for two
       weekends), to construct a new puffin crossing on A149 Cromer  separate diversion routes is so delays to through traffic will be kept
       Road (near the recreation ground) and also to resurface the existing  to a minimum.
       carriageway on A149 Hunstanton - Cromer Road and A149 Old  Access to any properties and businesses within the limits of the
       Hunstanton - Old Hunstanton Road.  It will be necessary to close  works will be maintained from one end of the closure at all times,
       sections of the road throughout the works which will be carried out  but it is inevitable that there will be delays.
       in 3 phases to minimise disruption to all road users where possible.
        With  reference  to  drawing  number  PM3063-HP2-004B  the  Paul Gallop - Engineer
       current  programme  of  works,  which  is  subject  to  any  adverse  paul.gallop@norfolk.gov.uk      0344 800 8020
       weather conditions, is as follows: -
       Week 1 = 16 - 20 February:
       24  hour  road  closure.    As  it  is  necessary  to  excavate  the
       carriageway,  remove  the  existing  pedestrian  refuge  and  leave
       trenches  for  new  ducting  exposed  over  night  a  24hr  closure  is
       required for safety reasons.
       Week 2 and 3 = 23 February – 6 March:
       Road closure between 09:00 and 16:00 – At other times traffic
       lights will be used during peak times taking traffic through the
       centre of the carriageway.
       Week 4, 5 and 6 = 9 - 27 March:
       Road closure for surfacing and footway works.  Due to the size of
       plant required for the surfacing works and the requirement of a
       temporary pedestrian footway during the footway works, it is not
       safe to open the road using traffic lights during peak times to allow